You are here: Chargemaster Toolkit Help > Modules > Corporate Module > Standardize

Standardize

The Standardization process analyzes each of your clean facility files and identifies charge items similar to those in the designated Corporate Standard. The Standardization Wizard walks you through this process in stages. You examine the charges identified and decide whether they should be mapped to the Corporate Standard.

You must ensure that all files to be included in the Standardization process are checked-in before preparing to run the Standardization Wizard. (Ensure that no other user has any files checked out.)

You should check out only the departments that you want to Standardize (in both the Corporate Standard file and any corresponding facility files).

You do not have to perform the whole Standardization process ‘in one go.’ Indeed, you do not even need to perform the ‘whole’ Standardization process. At the end of each of the five steps of the process you are offered the option to ‘Finish.’ If you decide to ‘Finish’ you are then offered the chance to save the changes (save the Standardization up to that point) and the files are then automatically checked-in. (Whether you save the changes or not, the files are always automatically checked-in after clicking on the Finish button, regardless of the ‘stage’ of the Standardization process.)

  1. From the main menu select File > Review. [Picture]
  1. Select your Corporate Standard file then click on the Review button. The User Login screen displays. [Picture]

In this example the Corporate Standard file is called ‘Corporate Standard.’ You may name the file anything you wish in the ‘file preparation’ stage — as long as you inform Craneware.

  1. Enter your user name and password in the fields then click on the OK button. The Department Selection/Checkout screen displays. [Picture]
  1. Select the departments you want to standardize then click on the Finish button. The Standardization Options screen displays. [Picture]

You should check out only the departments that you want to standardize (in both the Corporate Standard file and any corresponding facility files).

  1. Select the facilities you want to include in the Standardization process then click on the OK button. The Select Departments for Standardization screen displays. [Picture]

You may further refine how you want the process to treat your selections using the four check boxes at the bottom-left of the screen.

A facility may be standardized with the Corporate Standard either individually or simultaneously with other facilities; the result is the same. New facilities may be added at a later date, if necessary.

  1. For each facility selected (using the tabs), choose the departments you wish to include in the mapping process then click on the OK button. The Loading Facility Files screen displays followed by a screen informing you of the progress of the Standardization Wizard; this screen then provides some statistics. (The first step of the Wizard checks for charge items that have been mapped previously.) [Picture]
  1. When you have examined the (previously mapped charge items) statistics to your satisfaction click on the Close button. The Corporate Standardization Wizard displays all charge items previously mapped to the Corporate Standard. [Picture]

In the example shown here there are a number of charge items that have been previously mapped to the Corporate Standard. (Charge items that have been previously mapped are colored blue.)

If this is the first time you have run the Standardization Wizard the grid will be empty (as no charge items could have been previously mapped).

  1. Right-click on a charge item to display the pop-up menu shown below. The menu has tools that you can use to help you make decisions as to whether the mapped charge should be mapped to the Corporate Standard or not. [Picture]
  2. Info
  3. Add Memo
  4. Search Code Book for...
  5. Undo Corporate Map
  6. Select all
  1. When you are done click on the Next button. The Corporate Standardization Wizard moves to step 2 of 5. A screen detailing some mapping statistics displays followed by the screen below. This screen displays the automatic mappings made by the Corporate Standardization Wizard. You can review the mappings using the tools described below. [Picture]
  2. Right-click on a charge item to display the pop-up menu. The menu has items that you can use to help you make decisions as to whether the mapped charge should be mapped to the Corporate Standard or not.
  3. When you are done click on the Next button. The Corporate Standardization Wizard moves to step 3 of 5. A screen detailing some mapping statistics displays. [Picture]
  4. This step looks for charges that may require manual mapping. Click on the Close button. The Corporate Standardization Wizard — Step 3 of 5 screen displays. [Picture]

This step allows you to manually map charge items. The top half of the screen displays all charge items that require manual mapping and the bottom half of the screen displays suggestions for possible mappings (charge items similar to the charge item selected in the top half of the screen).

  1. Select a tab (that represents a facility) then right-click on a charge item in the top half of the screen. A pop-up menu displays. [Picture]

The first three items are the same as pop-ups in previous steps of the Standardization Wizard: Info, Add Memo, and Search Code Book for...

The next five items in the pop-up menu allow you to replace and map charge items.

Replace With…

Offers one or more alternatives from the Corporate Standard that you can use to replace the charge item in the facility file. (This action does not map the charge item.)

If there is more than one field different between the Corporate Standard and the facility file you will be offered two separate Replace options.

Map To…

Maps the charge item to the selected charge in the Corporate Standard file. (The facility charge item is mapped to the charge item in the Corporate Standard but no changes are made to the charge item.)

Replace with… And Map To…

The charge item in the facility file is replaced with the selected charge item from the Corporate Standard then mapped to the selected charge item in the Corporate Standard.

Add to Corporate Standard

Adds the facility charge item to the Corporate Standard. The (new) charge item in the Corporate Standard is then automatically mapped to the original charge item in the facility file. (The next time you run the Standardization Wizard it will try to identify and may suggest additional mappings from other facility files.)

Local Facility Charge Item

Assigns a charge item the designation of ‘Local Charge’ status. A Local Facility Charge Item is one which does not have an equivalent corporate charge item to map to. Usually it is a charge item which is particular to just one facility.

  1. Click on the Next button. The Wizard moves to step 4 of the Corporate Standardization Wizard. A screen detailing some mapping statistics displays. [Picture]
  2. Click on the Close button. The Corporate Standardization Wizard — Step 4 of 5 screen displays.  [Picture]

Now the Standardization Wizard performs an Intent of Service check on the remaining unmapped charge items. The wizard will identify possible matching Corporate charge items and place them in the lower pane with the ‘most likely’ matches toward the top of the list.

  1. Select a tab (that represents a facility) then right-click on a charge item in the top half of the screen. A pop-up menu displays. [Picture]

The first three items are the same as pop-ups in previous steps of the Standardization Wizard: Info, Add Memo, and Search Code Book...

The next five items in the pop-up menu allow you to replace and map charge items.

Replace With…

Offers one or more alternatives from the Corporate Standard that you can use to replace the charge item in the facility file. (This action does not map the charge item.)

If there is more than one field different between the Corporate Standard and the facility file you will be offered two separate Replace options.

Map To…

Maps the charge item to the selected charge in the Corporate Standard file. (The facility charge item is mapped to the charge item in the Corporate Standard but no changes are made to the charge item.)

Replace with… And Map To…

The charge item in the facility file is replaced with the selected charge item from the Corporate Standard then mapped to the selected charge item in the Corporate Standard.

Add to Corporate Standard

Adds the facility charge item to the Corporate Standard. The (new) charge item in the Corporate Standard is then automatically mapped to the original charge item in the facility file. (The next time you run the Standardization Wizard it will try to identify and may suggest additional mappings from other facility files.)

Local Facility Charge Item

Assigns a charge item the designation of ‘Local Charge’ status. A Local Facility Charge Item is one which does not have an equivalent corporate charge to map to. Usually it is a charge item which is particular to just one facility.

  1. When you are done click on the Next button. The Wizard moves to step 5 of the Standardization Wizard. A screen showing the remaining (unmapped) charge items displays. [Picture]

This final stage of the Standardization Wizard requires that you map from tabs in the main window (Corporate Standard file) of the Chargemaster Toolkit to the charge items displaying in the Corporate Standardization Wizard window.

  1. Right-click on a charge item. A pop-up menu displays. [Picture]

Map To…

Maps the charge item to the selected charge in the Corporate Standard file. (The facility charge item is mapped to the charge item in the Corporate Standard but no changes are made to the charge item.)

Add to Corporate Standard

Adds the facility charge item to the Corporate Standard. The (new) charge item in the Corporate Standard is then automatically mapped to the original charge item in the facility file. (The next time you run the Standardization Wizard it will try to identify and may suggest additional mappings from other facility files.)

Local Facility Charge Item

Assigns a charge item the designation of ‘Local Charge’ status. A Local Facility Charge Item is one which does not have an equivalent corporate charge to map to. Usually it is a charge item which is particular to just one facility.

  1. When you are done click on the Finish button. [Picture]
  2. Click on the Yes button (unless you want to discard the Standardization — in which case select the No button). If you want to keep the GLs checked out you must check the Retain lock... box.

The Standardization is complete and the files are checked in (the files are checked in automatically whether you keep the Standardization or not).

 

____________________________________________________________________________________________________________________________________